Independent research / Nuclear energy
Aurora-INL deployment evidence
A public-source model of a reactor built twice: once on site, once in evidence.
Reviewed 14 July 2026. This is an independent analytical model, not an Oklo schedule, authorization statement, or proprietary design disclosure.
Site basis
Establish the Aurora-INL site basis
INL places Aurora south of the Materials and Fuels Complex and reports site-characterization and geotechnical work.
Evidence reel / paused while offscreen
Browse all frames
Expert brief / 01
Confirmed public fact- Physical work
- Define the disturbance area and characterize the conditions that later work must respect.
- Evidence work
- Keep site assumptions, environmental boundaries, and interface responsibilities traceable.
Public-record boundary
A location and early site basis are public. Detailed site-design outputs are not.Working vocabulary
INLIdaho National Laboratory
MFCMaterials and Fuels Complex
Primary references
Method and limits
Public evidence is not a construction schedule.
The first five stages are bounded by public early-work records. DOE safety-basis work, NRC pre-application activity, and the A3F fuel pathway progress on different evidence streams. Later details are deliberately marked as inference or unknown.